公司動態(tài) | 本周生產(chǎn)速遞 — 多項目并行推進(jìn),生產(chǎn)節(jié)奏穩(wěn)健
——Multi-Project Progress with Stable Workflow
發(fā)布時間:2025-07-29 09:44:20 人氣:
公司動態(tài) | 本周生產(chǎn)速遞 — 多項目并行推進(jìn),生產(chǎn)節(jié)奏穩(wěn)健
雷波 40,000/110?kV 變壓器
進(jìn)行高壓線圈預(yù)干燥及低壓線圈組合工序。預(yù)干燥通過溫控下對繞組加熱,使絕緣中殘余水分蒸發(fā)脫出,從而確保絕緣性能和長期可靠性。兩臺改造電爐(6300/35?kV)
已完成高低壓線圈繞制。線圈采用張力控制、自動縫合,并大量使用換位導(dǎo)線和復(fù)合導(dǎo)線,最大程度降低附加損耗,同時確保結(jié)構(gòu)緊湊、性能穩(wěn)定。攀枝花 3,150/10?kV 變壓器
進(jìn)入整機組裝階段,包括鐵心心柱插片、引線布置及絕緣組件安裝,隨后進(jìn)入調(diào)壓及出廠測試工序。15,000×2/110?kV 整流變項目
第?3?1 臺:鐵心疊片已完成,已進(jìn)行氣隙和疊片對齊檢測;
第?2?1 臺:器身套裝同步進(jìn)行,配件及結(jié)構(gòu)就緒,隨時進(jìn)入干燥及測試流程。
出口 70,000/220?kV 項目
器身引線裝配正在進(jìn)行中,采用進(jìn)口冷壓焊接技術(shù),確保連接電阻低、耐用性強。油品入廠
今日接收兩車級別為 25號變壓器油。該油號代表定級油品,滿足IEC?60296與GB12536?90標(biāo)準(zhǔn),具有高擊穿電壓、低含水量、優(yōu)良抗氧化特性,是保障高壓變壓器絕緣和散熱功能的重要材料。
小結(jié)
本周,多個項目圍繞繞制、預(yù)干燥、裝配和材料檢驗同步推進(jìn)。每一環(huán)節(jié)均體現(xiàn)公司在工藝選擇、技術(shù)控制及質(zhì)量監(jiān)控方面的專業(yè)性。我們將繼續(xù)恪守“精準(zhǔn)制造、規(guī)范流程、準(zhǔn)時交付”原則,全力保障客戶滿意與設(shè)備長期穩(wěn)定運行。
Corporate News | Weekly Production Update — Multi-Project Progress with Stable Workflow
Date: July 2025
Leibo 40,000 / 110?kV Transformer
Undergoing high-voltage coil pre?drying and low-voltage coil assembly. Pre?drying involves controlled heating to remove residual moisture within winding insulation, ensuring dielectric strength and long-term reliability.Two Rebuilt 6,300 / 35?kV Furnace Units
Coil winding for both high and low voltage circuits is complete. Tension control, automatic seam stitching, and the use of transposed and composite conductors minimize eddy losses while maintaining coil compactness and structural integrity.Panzhihua 3,150 / 10?kV Transformer
Now in full assembly phase, including core column insertion, lead layout, and insulation assembly. Next steps include tap adjustment and factory acceptance testing.15,000 × 2 / 110?kV Rectifier Transformer Project
Unit 3?1: Core lamination stacking is complete and has passed gap and alignment inspections.
Unit 2?1: Body assembly is in progress with components ready, soon moving into drying and testing stages.
Export-Bound 70,000 / 220?kV Main Transformer
Currently in lead assembly stage, using imported cold?pressure welding technology to ensure low resistance and high durability connections.Transformer Oil Delivery
Two trucks of grade?25 transformer oil arrived today, where “25” denotes the specification grade. This mineral insulating oil meets IEC?60296 and GB12536?90 standards and features high dielectric strength, low water content, and excellent oxidation resistance—critical for high-voltage transformer insulation and cooling.
Summary
This week's production progress includes coil winding, pre-drying, assembly, and materials acceptance across multiple projects. Each procedure reflects our expertise in technical selection, process control, and quality supervision. We remain dedicated to our motto: Precision Manufacture → Standardized Procedure → Timely Delivery, ensuring client satisfaction and equipment reliability.
- 2025-04公司動態(tài)|重載前行,穩(wěn)達(dá)山巔--260000kVA/220kV主變壓器穿越貴州山區(qū)運輸紀(jì)實
- 2025-04公司動態(tài)|重要節(jié)點 —— 第二臺260000/220kV主變順利交
- 2025-04公司動態(tài)|節(jié)后開工有序生產(chǎn),嚴(yán)把質(zhì)量高效交付
- 2025-04公司動態(tài) | 260000/220kV 變壓器順利通過測試并啟運交付
- 2025-02公司新聞 | 植物油變壓器出口瑞典,助力全球綠色能源發(fā)展
- 2024-11我公司造250000kVA/220kV自耦變壓器順利出廠發(fā)運吉爾吉斯斯坦
- 2024-03二三月生日團(tuán)建會
- 2024-03縣領(lǐng)導(dǎo)李建康到成都雙星調(diào)研“開門紅”工作